Of the measures of feasibility in the accompanying figure, issues that relate to ____ include "Has management established a firm timetable for the project?" and "Will a project manager be appointed?"
a. schedule feasibility
b. technical feasibility
c. economic feasibility
d. operational feasibility
Answer: A