PERT/CPM is called a(n) ____ technique because it analyzes a large, complex project as a series of individual tasks. Compiler Design PERT/CPM is called a(n) ____ technique because it analyzes a large, complex project as a series of individual tasks. a. top-down c. indexed b. bottom-up d. cataloging Answer: B Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+