The first step in the creation of a PERT/CPM chart is to ____. Compiler Design The first step in the creation of a PERT/CPM chart is to ____. a. determine the logical order of project tasks b. identify the graphical planning aids to use c. identify all the project tasks d. determine the status of all tasks Answer: C Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+